Critical Chain Project Management (CCPM): All You Need to Know

When you embark on a project, you plan to succeed, but few projects are without their problems. Critical Chain Project Management (CCPM) was added to the Project Management Body of Knowledge (PMBOK) in 1996, and it aims to do away with frequently-encountered issues that can lead to a poorly performing or failed project.

CCPM methods help project managers to focus on the project’s schedule, but they also help to reduce changes to the project that are implemented once it is underway. After all, it’s harder to shoot at a moving target or accomplish a goal when the goalposts keep moving. The most successful projects are completed within the planned timeframe using the planned resources. When they don’t, cost overruns are almost inevitable.

So far so good, but you’re probably wondering, is the Critical Chain Project Management (CCPM) approach actually used? After all, beautiful-sounding theories don’t necessarily work well in practice.

Well, the long roll of companies that have implemented CCPM and experienced improved project performance is impressive. Big names like Texas Instruments, Harris Semiconductor, and Lucent Technologies report spending half, or even less than half the time they needed to complete similar projects after implementing CCPM.

Critical Chain Project Management – The Theory

CCPM consists of three theories. Before we look at the practical application of CCPM, we need to understand the thinking that goes into it.

1. Theory of Constraints

This theory may seem all-too-obvious, but sometimes, the obvious becomes easy to overlook. The theory of constraints says that any system will have constraints that govern its output. To focus on constraints, we follow five steps:

  1. Identify the relevant constraint
  2. Exploit it (get it working at 100% capacity)
  3. Subordinate all other elements of the system to the constraint
  4. Elevate the constraint (add resources to reduce the constraint, but only if it isn’t broken in steps one to three)
  5. Keep focusing on every possible constraint using the four steps mentioned above

2. Common Cause Variation

There are two types of variation. Common Cause Variation is part of the system as a whole. Special Cause Variation has a specific source such as a team, an employee, a machine, or a circumstance.

Common Cause Variation applies to projects because it affects the time needed to perform part of any project. Let’s say you have several teams. On the surface, they work independently, but one team can’t start working until the other team has finished its work. The obvious effect will be variations stemming from the interdependence of activities.

To make this clearer, let’s say you flip a coin. You might expect to have a 50/50 distribution of heads vs tails, but the fewer the times you flip the coin, the more likely you are to get a skewed result. Cumulative probability effects mean that the more tasks there are, the more likely we are to get a median result.

What is Tallyfy?

Tallyfy helps you document and automate tasks between co-workers and clients

Click here to learn about Tallyfy

3. Statistical Laws Govern Common Cause Variation

Let’s suppose we have a chain of activities. Each activity in the chain has a 50 percent likelihood of finishing within a day. But there’s a 90 percent probability that the activities will take two days. Supposing that there are four activities in the chain, scheduling them to take eight days makes sense on the surface. However, there’s a strong possibility that we could finish sooner.

If we use the statistical law of aggregation, we can achieve a 90 percent probability by scheduling the activities at 50 percent of the worst-case estimate of eight days. Just to be on the safe side, we can add a two-day buffer. Thus, instead of scheduling eight days for the chain of activities, we can schedule them for six days.

We also need to remember the central limit theorem. In simple terms, this means that the larger the sample, the better its chances of achieving a normal distribution. In projects, we find many tasks that have a minimum possible time needed and then the possibility of taking a lot longer that. We saw that in the graph we looked at a little earlier on.

However, the central limit theorem says that the combination of many activities would have a more symmetrical distribution than we saw in our graph.

Critical Change Project Management (CCPM) Solves Problems Other Methods Overlook

Using the central theories we just discussed, Critical Chain Project Management strives to eliminate undesired effects that make projects longer and costlier than we planned. We know the theories. Now, we look at what CCPM addresses when compared to a traditional approach. Armed with this knowledge, we’re ready to embark on the process.

1. Eliminate Overly Long Estimates of How Long Things Take

Project managers are already very well aware that the minimum time things take and the actual time it takes to get them done can vary greatly. As a result, they tend to play it safe when it comes to time estimates.

They get their information from people who already know the job that must be done. What they don’t give, though, is the probability of that estimate being correct. If you return to the graph illustrating probability vs. cumulative probability, you’ll see that a low-risk estimate could be twice as long as the one with a 50 percent probability of being accurate.

With project participants and project managers tacking on a contingency time to be sure work will finish on schedule, overall projects end up covering a whole lot more time than they really need to.

2. Wasting Time Waiting for Things to Get Urgent

With lots of time to get things done, most people involved in a project will report timely completion. But about ten percent of them will report late completion. Given that the project has played safe with a 99 percent probability of timely completion, 99 percent of activities should finish on time or even earlier than expected. Why does this happen?

Let’s think back to the time when you were a student. You knew that you’d be writing exams at the end of the semester. During the semester, you probably did about one-third of what you needed to do to prepare for the exam. But in the last third of the semester, when D-Day drew nearer, you tried to get two-thirds of your studying done. “I didn’t have enough time to prepare for the exam!” you said.

The truth is, you did have enough time. You just tried to get everything done at the last minute. The phenomenon of planned procrastination is often referred to as “student syndrome,” and it’s human nature. People tend to drag their feet until things get urgent, and the same is true of projects. You’ve probably heard the saying “Work expands to fill available time,” it’s true!

student syndrome graph

Image Source: PlaybookHQ

Did you follow this pattern when you were a student? Are you project teams following it too?

3. Failing to Pass on Time or Resources Saved

Failing to pass on savings is a very real problem in projects. Again, human nature has a role to play. If you’re part of a project, you’ll be rewarded for finishing on time, and you’ll be punished if you finish late. If you finish early, on the other hand, you don’t get anything. In fact, you could end up getting less than you’d have received if you finished on time because you spent less time getting things done.

The same is true of materials or resource savings. If you use less than was first supposed, there’s nothing in it for you. On the contrary, you might lose out. So, what do you do? You down-prioritize resource savings and time savings. You overwork steps that could have been reported as finished long ago, and so on.

4. Delays as a Result of Activity Paths Merging

When you’re busy with a project, be it simple or complex, several things are usually happening simultaneously. At some point, usually near the end of a project phase, everything starts coming together.

There’s just one problem: if the merging activity paths consist of three paths, and one of them is early, the second on time, and the last late, the phase isn’t complete till the late activity is finished. That makes all three processes as late as the one that got completed last of all.

Older analysis techniques like Critical Path Analysis don’t allow for path convergence delays.

6. Delays Because of Multitasking

We usually think of multitasking as being a “good thing,” but in the context of projects, it causes delays. It’s easy to understand why. Let’s suppose that you are busy with four activities and that each of them takes a week to finish. Because you’re multitasking, you don’t finish any of them in a week. You split your day up into segments, and each task ends up taking four weeks to complete.

Supposing that this is the way you usually work, you’ll end up budgeting four weeks for a task that should take only one week. The result? A project that takes longer than necessary to finish. Interestingly, research has shown that we just aren’t wired for multitasking. So, we can add the fact that the total time needed for each task is longer than it ought to be too.

7. Losing Focus in Areas on Which You Should be Focusing

As a project manager, there are a lot of things to distract you from the priorities where your focus is most urgently required. These could include:

  • All activity paths starting simultaneously
  • Changes that occur during project performance
  • Using dollar value instead of schedule performance as a measurement
  • Spending time addressing variances that fall within acceptable parameters

The Critical Chain Project Management Process

Now that we have a (very basic) understanding of the theory behind Critical Chain Project Management (CCPM), and the problems it tries to eliminate, we can examine just how to do it. Here’s how we can finish projects sooner and avoid the pitfalls of traditional project management.

1. Exploit the Constraint

Up till now, your project management activities have been based on constraint after constraint. This might happen late, or that might happen late, so you budget more time than you really need just so that you can get finished on time.

The first step is to get the people who estimate the time needed for a task on the same page as you are. First, they need to know what you’re trying to achieve. No, you do not want the “safest” estimate alone.  Instead, you want the average time in which an activity can be completed supposing that everything goes well. You also want the low-risk estimate they’d usually give.

Now that you have that info, you can start constructing your critical chain using the average time, plus a buffer that’s midway between best and worst-case scenarios.

2. Subordinate Chain Paths That Aren’t Critical

Most project managers allow noncritical paths to start early. They reason that by doing so, these paths have enough leeway to get finished in time. Use this approach, and the noncritical path participants know they’ve got lots of slack to play with. They’ll use it to the full.

With CCPM, you’ll use late start schedules, and you’ll build in a reasonable buffer, but you won’t necessarily plan for a worst-case scenario.

3. Use Buffer Times Effectively

In Critical Chain Project Management, you don’t add a buffer to every deadline. Instead, you place it at the end of the critical chain. By doing so, you can exploit the law of aggregation which we discussed a little earlier. The buffer is listed as an activity itself, but you don’t specify what work might fill it.

The simplest way to calculate buffers is to add up all the activity time-frames. Half of that total represents your buffer. This buffer is shared among all activities, so if one is late and another can’t start because the previous one was overdue, there’s time to set things to rights.

4. Buffers for Subordinate Paths

A critical chain consists of subordinate paths that feed into the critical chain. Project managers must protect the critical chain by providing potential buffer time to use at the point where each subordinate chain feeds into the chain.

By doing this, you can protect your critical path from delays in subordinate paths. And if those delays don’t materialize, your project speeds ahead towards an early delivery date.

6. Resource Buffers

Now, it’s time to do away with overruns on resources. You’ll only apply resource buffers to the critical chain, not the subordinate ones. When you’re working on a project that carries a lot of risk, or if you’re using subcontractors, financial incentives could be among the resource buffers you apply.

That means that you can incentivize early delivery instead of penalizing it, and you can build in penalties for late delivery. The feeding chains don’t get these buffers because you’ve already added time buffers at the end of each one.

The Critical Chain and People

We’ve already seen that typical human behavior patterns affect project performance. CCPM overcomes these behaviors. Here’s how:

1. Ditch “Student Syndrome” Date-Driven Delays

Instead of giving dates for individual activities, you only provide dates for completion of the activity chains as well as the buffer time. Now, the teams engaged in the project aren’t focused on deadlines they can delay. Instead, they focus on finishing as soon as possible.

Start dates for the rest of the critical chain are approximations and aren’t cast in stone. Because you’re planning according to best-case completion times, you don’t impose penalties for being late if work started when the resources were available, people and teams aren’t multitasking, and they pass on the completed activity as soon as they are finished.

2. Eliminate Multitasking

As a project manager implementing CCPM, you will expect 100 percent focus on the task at hand from every individual and team.

Multitasking would be fine if you could do several things at once and still focus on each one to the full. However, that’s not humanly possible, so multitasking goes out the window.

3. Buffers and Managers

We saw that project managers often lose focus on a project because they are giving attention to processes or tasks that still fall within an acceptable variance. In CCPM, the buffer time is the indicator of when trouble may be brewing.

You’re expecting to use at least some of the buffer time to tie up loose ends, so the first third of it doesn’t yet represent a time when the project manager needs to intervene.

Once the delay enters the second third of the buffer period, it’s time to start examining the situation a little more closely. Is there a problem, how much of a problem is it, and what should be done?

The last third of the buffer indicates the time when managers initiate contingency plans to get things back on track. By applying this approach to management by exception, project managers avoid spending time on unnecessary interventions.

4. What if You are Managing Several Projects at Once?

Although it would be wonderful to focus all your effort on one project at a time, the truth is that you, as a project manager, are probably taking care of several projects at once. What do you do now?

The answer is to determine what the multitasking constraint is. Where is capacity likely to be constrained? Is it the availability of qualified personnel? If these constraints can’t be overcome in a multi-project environment, you will set the rhythm for the management of your project based on the limitations you can’t eliminate. Simplifying matters could be as easy as adding capacity buffers between several simultaneous, synchronized projects. If the constraining factor doesn’t overrun the buffer time, everything is still on track, and if all the buffer time isn’t needed, the project can be moved forward and completed early.

5. Critical Chain Project Management (CCPM) and Resources

Since resources can never be infinite, resource allocation must be prioritized. Prioritize resources using these criteria:

  • Critical chain activities take precedence over no-critical activities
  • Activities that have the greatest potential to penetrate the project buffer over ones that haven’t.
  • Activities that penetrate feeding buffers to the greatest extent over ones that have lower buffer penetration.

CCPM is Relatively Simple

Compared to other project management techniques like PERT, Monte Carlo Methods, and earned value methods, CCPM is relatively straightforward. When project managers can monitor buffer penetration in real-time, they will have enough time to help the process along so that it can finish before the buffer time is over. They know when to start examining delays more closely, and they know when it is time to intervene.

The planning process is also simplified and doesn’t require any specialized software tools. However, software remains useful in the monitoring of project progress. Tallyfy provides a clean, simple, and effective means of monitoring project progress in real time.

A Quick Summary of CCPM

When Working on Single Projects

  • Capture the critical chain with an eye to resource constraints.
  • Reduce the times you’d ordinarily use to the point where they have a 50/50 chance of being complete (aggregation will help these to be realistic).
  • Place a buffer time at the end of the critical chain.
  • Add buffers to subordinate chains that feed into the critical chain.
  • Add resource buffers that will ensure you have the resources you need when you need them.

When working on multiple projects simultaneously

  • Know which resource will constrain progress
  • Create a schedule for that resource
  • Adjust project sequence to match the constraining factor
  • Add buffers based on resource constraints or capacity limitations

Measurements and Controls

  • Buffer management will be the area of focus for project managers.
  • Assign resources based on buffer information.

Finally, ensure that you’re not incentivizing or encouraging late completion because you didn’t take the human element into account.

Why adopt CCPM? If you do so, you stand to complete projects faster and more cheaply. The Project Management Institute (PMI) reports that Critical Chain Project Management (CCPM) can reduce the time needed to complete projects by 50 percent or more. Now, that’s something to celebrate!

Is this post written for a search engine or for you?

Many B2B cloud software companies invest in blog posts in the hope of ranking high on search engines like Google. What they’re doing is writing articles around keywords, which are terms customers are likely to search for on Google. The posts don’t offer valuable information or make any sense.

But then if you’re reading something that doesn’t make sense, how are you supposed to make informed buying decisions?

We have a lot to say about workflow and business processes. We truly believe in continuous improvement. But it’s not really about us. We publish these articles to help you find Tallyfy, and to provide you with information that will help you make informed buying decisions.

Ready to automate your workflows? Check out Tallyfy.

How exactly do we conduct research?

We research topics down to the bone. We nitpick, we argue about what to keep and what to throw out. It’s a lot of work. We consult academic sources for scholarly citations to support our points. We gather data to summarize particular points. At Tallyfy – 3 independent experts validate and edit every article from the draft stage. That includes verifying facts and their sources.

Why did we write this article?

Tallyfy believes in helpful and authoritative content that helps people. Our customers requested us to write about this topic so we attempted to put together the highest quality article available anywhere – that’s our goal. Work like this takes a lot of effort. If you liked this article please share the link with your coworkers via email, or on LinkedIn.

About the author - Amit Kothari

Related Posts

Say goodbye to workflow chaos. Simplify with Tallyfy.

Turn messy business processes between coworkers and clients into smooth, digitized workflows that anyone can track in real-time

  • Eliminate Admin Time – Win back 2 hours per person per day
  • Automate & Track – Delegate tasks, track in real-time and stay in control
  • Ensure Consistency – Standardize high quality outcomes across your operations
  • Organizations in get a discount for life!

Track all your workflows beautifully - on Tallyfy